An owner may apply for to a Territorial Authority for a Certificate of Acceptance (COA) in the following instances:
Where building work undertaken after 1 January 1993 required a building consent but one was not obtained.
Where a building consent was approved by a building consent authority other than this Council. For example, private certifiers and a Code Compliance Certificate has not been issued.
Where urgent work as defined in Section 41(1)(1) of the Building Act has been completed without a building consent. ‘Urgent work’ means work that is “for the purpose of saving or protecting life or health or preventing serious damage to property or ensuring a specified system is made safe”. In the case of urgent work, the owner must apply for a COA “as soon as practicable after completion of the work”.
Please note you MUST have a pre application meeting before an application for a COA can be lodged.
There is a popular misconception that applying for a COA as provided for in section 96-99 of the Building Act 2004 (the Act) will result in an owner being issued with a certificate that has similar status to a Code Compliance Certificate issued under sections 91-95 of the Act. This is not the case. A COA, if issued, is likely to cover only limited aspects of the building work that was undertaken.
Once building work has been completed we are often unable to undertake all types of inspections carried out during construction. It may not therefore be possible to establish if all building code requirements have been met. Therefore, Certificate of Acceptances issued are limited and “qualified to the effect that only parts (if any) of the building work were able to be verified as complying with the Building Code”.
A COA does not relieve the owner of the building (or proposed building) of any duty or responsibility under any other Act relating to or affecting the building (or proposed building). A COA also does not permit the construction, alteration, demolition, or removal of the building (or proposed building) if that construction, alteration, demolition, or removal would be in breach of any other Act.
The granting of a COA does not remove the need to obtain a retrospective resource consent if one is required under the Central Hawke's Bay District Plan.
An application for a Certificate of Acceptance will not be accepted where:
Also an application for a COA may not always be the best or most economic option when Council has declined to issue a Code Compliance Certificate where a private certifier approved the building consent, undertook inspection/s but did not issue a Code Compliance Certificate.
In some cases, an application to the Ministry of Business Innovation and Employment (MBIE) for a determination may be appropriate. Please refer to the MBIE determination information for further information.
Council charges a fee for the processing of an application for a Certificate of Acceptance, for further details please see our fees & charges on our website.
Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is
accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz