The nature of Central Hawkes Bay terrain and the low traffic volumes (although a high volume of slow-moving trucks) has meant that its rural strategic routes have been built as two-lane highways (now HPMV routes).
As slow-moving vehicle volumes have increased, pressures have been placed on the existing level of service. Passing opportunities are limited and often on straights where forward sight distance is poor.
Central Hawke’s Bay District Council (CHBDC) asked Stantec to investigate locations that could be considered for an overtaking lane along Porangahau Road as previous engagement had revealed certain stakeholders were being held up by the increasing number of heavy vehicles (HCV’s) using this route, predominantly logging trucks.
During discussions it was agreed a better strategy would be to investigate multiple sites for Slow Vehicle Bays (SVB) as the preferred locations for overtaking lanes were predominantly on the flat and there would be minimal speed differential between these HCV’s and other traffic; these SVB locations would provide more benefit to the local community than an overtaking lane.
Slow vehicle bays provide a means to relieve these risks and improve the level of service to the general public. When drivers are unable to overtake slower vehicles, they are likely to become frustrated and perform a risky, unsafe passing manoeuvres that could lead to an accident.
This project has been launched with Stantec having produced a technical memo that identifies five slow vehicle bay sites on Porangahau Road for investigation, as well as providing recommendations with regards to which of these site(s) should progress through to detailed design.
The five sites investigated were selected based on the speed differential of HCV’s, the geometry of the road (as this also provided a natural deceleration location for HCV’s) and a visual assessment of the ease of construction compared to other sites along the route.
Site 1 (preferred by the NZ Police and the local School bus driver) will require geotechnical investigations; however, the surrounding slopes are flatter than all of the other sites and it could be extended downhill or if preferred a short SVB established at Site 2 that is located away from a natural pond.
You can view a map of the Slow Vehicle Bays Project here.
We recently sealed our new slow vehicle bay on Pōrangahau Road, and once signs are installed on the lead up, the cones will be removed and the slow vehicle bay will open for traffic!
Following community feedback on possible locations in 2021, construction started in early 2022 to build the (nearly) 500m slow vehicle bay. This bay aims to improve safety on the road and allow vehicles to safely pass slower vehicles on their commute north.
Our contractors are doing final drainage and underground pipe checks to confirm everything is working correctly. Once this is complete, the cones will be removed and the road will be fully reopened. We expect this will happen by Friday 15 July.
Big thanks to our contract partners Russell Roads and Stantec for their mahi on this!
Last year we asked for feedback on a proposed slow vehicle bay to be positioned on Pōrangahau Road to allow road users to safely pass trucks.
After moving forward with the preferred option, works have started to create the slow vehicle bay. As you can see in the image below, Russell Roads are on site and earthworks are well underway to widen this section of Pōrangahau Road.
Works will continue over the next month with a completion date set for June 2022.
Work to widen the road for the new slow vehicle bay on Porangahau Road
After moving forward with the preferred option, works have started to create the slow vehicle bay. As you can see in the image below, Russell Roads are on site and earthworks are well underway to widen this section of Pōrangahau Road.
Works will continue over the next month with a completion date set for June 2022
Last year we asked for feedback on a proposed slow vehicle bay to be positioned on Pōrangahau Road to allow road users to safely pass heavy laden vehicles.
Thank you to those who provided feedback to us - we had feedback on 7 different locations, with location #1 being the clear preferred option, seeing a slow vehicle bay northbound, approximately 12km out of Waipukurau.
We are pleased to advise that through the PGF programme we have made progress on the design for this location, and works will commence on-site to build a 600m long Slow Vehicle Bay. Russell Roads were awarded this work.
Works are planned to run from early February 2022 through to completion in June 2022.
Site clearance began this week and is now 90% complete. Testing of the subgrade material began which is key before earthworks begin.
43m of drainage installed
12353 litres of bitumen used
4751m2 of chipseal installed
350m of fencing installed
4435 total hours worked on the project
53 people working on the project
Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is
accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz