Retaining Wall Construction & Lower Wimbledon Retreat

The PGF funding agreement identified scope to address the retaining wall assets on the two roads by lifting them to accommodate HPMV loadings and increasing resilience. Stantec undertook a series of retaining wall condition assessments to prioritize the walls and identify other geotechnical risks evident along the route. 

There have been more than thirty retaining walls and geotechnical risks identified as significant along the route, with a dozen of these being recognized as being critical or high risk needing remediation or replacement.

PROJECT 1 - Contract 1075:

RW184 Porangahau Road - COMPLETE

  • Contractor: Downer
  • Construction: timber pole cantilever retaining wall with tieback anchors.  

RP@27488 Porangahau Road - COMPLETE

  • Contractor: Downer 
  • Construction: timber pole cantilever retaining wall with tieback anchors.  
PROJECT 2 - Contract 1076:

RW177 Porangahau Road - COMPLETE

  • Contractor: Russell Roads
  • Construction: A geogrid reinforced earth fill below the road to provide support to the existing road embankment. 

RW283 Wimbledon Road - COMPLETE

  • Contractor: Russell Roads 
  • Construction: steel pole cantilever retaining wall with tieback anchors. This wall is currently being completed after site issues caused delays. 
PROJECT 3 - Contract 1098:

RW277 Wimbledon Road -  COMPLETE

  • Contractor: Fulton Hogan
  • Construction: Installation of tieback anchors on existing railway iron to provide increased resilience. 
PROJECT 4:

RW440 - Porangahau Road - COMPLETE

  • Contractor: Higgins
  • Construction: Excavation of outside lane of road where river has eroded the bank and a geogrid reinforced earthfill will be constructed to support the road.

RW44– Wimbledon Road - COMPLETE

  • Contractor: Higgins
  • Construction: Excavation of outside lane of road where river has eroded the bank and a geogrid reinforced earthfill will be constructed to support the road.

Update - 02 October 2020

The retaining wall sites are across Porangahau and Wimbledon Roads.

IMG 1492

Update - September 2020

There are 8 sites being investigated for future retaining walls, one site covers essentially 3 features (two retaining walls with pavement deformation behind and a shoulder slump, 4 boreholes, over 140 m of road).  These have ended up as one “location’ as they are all part of the same feature, being a wide unstable slope through which the road passes.

Some photos of drilling this week so far for Retaining Walls:

RWs GI

CONTRACT-1075 - 2 x RETAINING WALLS ON PORANGAHAU ROAD (DOWNER)

The two retaining walls constructed by Downer on Porangahau Road are complete, one awaiting a guard rail.

24.12.20 Porangahau Rd RWalls 124.12.20 Porangahau Rd RWalls

UPDATE - 30 SEPTEMBER 2020

Backfill and road rehabilitation prep is underway, the project is close to completion.

C1075 Porangahau Road 300920

UPDATE - 28 SEPTEMBER 2020

C1075 Porangahau Road 280920

UPDATE - 17 SEPTEMBER 2020

C1075 Porangahau Road 170920

UPDATE - 15 SEPTEMBER 2020

C1075 Porangahau Road 150920

UPDATE - 03 SEPTEMBER 2020

Poles are due to go in this week.

C1075 Porangahau Road 030920

UPDATE - 01 SEPTEMBER 2020

Holes for poles are currently being dug and augered.

C1075 Porangahau Road 010920

UPDATE - 24 AUGUST 2020

Work is progressing well on site, last week the new poles were set out and concrete was poured at site #1 to set the poles in place.

IMG 0674

UPDATE - 27 JULY 2020

Work is progressing on two sites along Porangahau Road where new retaining walls are being installed to improve road resilience, stability and safety.

Downer RW Phau 25 July 2020

UPDATE - 12 JUNE 2020

Central Hawke’s Bay District Council has contracted Downer to strengthen two existing retaining walls on Porangahau Road, to account for the increased traffic being experienced along this major thoroughfare, and future proof for further growth.

Retaining wall 1: Located 27.5km from Waipukurau. Works due to start Monday 22 June (weather dependant).

C1075 Porangahau Road RW27488 Location

Retaining wall 2: Located 28.5km from Waipukurau. Works due to start on Monday 29 June (weather dependant).

C1075 Porangahau Road RW184 Location

Please account for minor delays to your journey, with the potential for single lane traffic being controlled by a stop/go system, through the course of the works.

Work is scheduled for completion Sunday 23 August, (weather dependant). Council apologise in advance for any disruption to your travel through this time. Please obey road signage on the work sites for the safety of all road users and construction staff.

For further information please contact the following:

Downer:

John Patten, Contract Manager – 027 232 5946

James Paston, Project Manager – 027 447 0221

Map of area pic Page 3

 

 

CONTRACT-1076 - 2 x RETAINING WALLS ON PORANGAHAU AND WIMBLEDON ROAD (RUSSELL ROADS)

UPDATE - Retaining Wall 283: MAY 2021 (Wimbledon Road) 

 This project is progressing well and is now at about 85% complete. The road now needs to be reinstated and a safety guard rail installed. 

 IMG 3395

UPDATE - Retaining Wall 283: 24 DECEMBER 2020 (Wimbledon Road)

24 of the 39 piles have been installed and the project is 70% complete, the site is now safe over the festive season and will be monitored over the break. Works are expected to restart onsite on the 11th Jan 2021 and be completed by early Feb 2021.

24.12.20 Wimbledon Rd RWalls

UPDATE - Retaining Wall 283: 23 SEPTEMBER 2020 (Wimbledon Road)

Ongoing management of the site to install the retaining wall is underway.

C1076 RW Wimb Russell Roads 230920

UPDATE - Retaining Wall 177: 18 SEPTEMBER 2020 (Porangahau Road)

C1076 Ret Wall Russell Roads 180920

UPDATE - Retaining Wall 283: 09 SEPTEMBER 2020 (Wimbledon Road)

Some concerns with the drop off and ability to manage the cut to establish the retaining wall is underway this week.

C1076 RW Wimb Russell Roads 090920

UPDATE - Retaining Wall 177: 09 SEPTEMBER 2020 (Porangahau Road)

Backfill commences and culvert install is underway.

C1076 Ret Wall Russell Roads 090920

UPDATE - 08 SEPTEMBER 2020 (Wimbledon Road)

Site is being established

C1076 RW Wimb Russell Roads 080920

UPDATE - Retaining Wall 177: 28 AUGUST 2020 (Porangahau Road)

Ongoing preparation for the retaining wall posts continue.

C1076 Ret Wall Russell Roads 280820

UPDATE - Retaining Wall 177: 19 AUGUST 2020 (Porangahau Road)

Ongoing preparation for the retaining wall posts continue.

190820 C1076 Phau Road

UPDATE - Retaining Wall 177: 10 AUGUST 2020 (Porangahau Road)

This week the team are removing fill to prepare for the retaining wall set out.

C1076 RW PGF Programme

UPDATE - 05 AUGUST 2020

Currently the team continues to excavate out for the retaining wall and does this in stages (known as benches). The next week will see this continue along with the installation of basecourse layers.

Sign 3 05.08.2020

UPDATE - 27 JULY 2020

The project is progressing well and the contractor is currently installing subsoil drainage before the retaining wall is constructed.

C1076 Drainage for RW

UPDATE - 10 JULY 2020

Russell Roads have commenced our second Quick Win project along this route - these projects have been identified as areas where we were able to deliver project fairly quickly along the route - the other projects along the route would take a bit longer the physically commence as we develop scope and design before getting a contractor onsite.

C1076 Signboard Project Commencement

UPDATE - 03 JULY 2020

The linked letter has been delivered to residents around the planned project sites - works are expected to commence shortly.

The locations of the two retaining walls are outlined below.

Retaining Wall 177 on Porangahau Road

C1076 Porangahau Road RW177 Location

Retaining Wall 283 on Wimbledon Road

C1076 Wimbledon Road RW283 Location

C1098 Retaining Wall 277 – Wimbledon Road

Update May 10, 2021

The overall construction of this retaining wall now sits at 75% completed. The riprap stone wall is completed and the work on the road reinstatement and the installation of a guard rail will commence this week.

IMG 4115
Update May 3, 2021:

Last week the team made great progress on the installation of the Riprap - a permanent layer of large, angular stone, used to stabilize and protect the soil surface against erosion and scour. The riprap on the face of the wall is expected to be finished this week with the overall project now 70% completed.

IMG 3846

Update March 2021:

Last week Fulton Hogan commenced work on our fifth retaining wall in the upgrade programme, the other four being undertaken by Downer and Russell Roads.

Fulton Hogan will be working with local contractor Tuck to build a new retaining wall on Wimbledon Road to safeguard the road from slips, and to build further safety and resilience on the route. We are finalising our programme scope, but expect to be building another 4 retaining walls along the route as part of this programme of works.

20210302 104037

Lower Wimbledon Retreat

We identified three risk sites along this 500m stretch on Wimbledon Road. During planning, it was found to be better value to undertake a retreat rather than address each site individually. This meant we needed to push the road 7m into the neighbouring paddock, moving it away from the subsiding edge, therefore alleviating risk of slope failure and further road degradation.

Trees were removed and the 500m retreat was built and completed in September 2022.

Lower Wimbledon Retreat Hero Image

Lower Wimbledon Retreat 2

Key Stats

123m3 concrete poured

2536m3 of granular fill used

290m of guardrail installed

268m of timber used

3620m2 of chipseal used

26 people working across the retaining walls programme

Loading...

Central Hawke's Bay District Council - Copyright © 2024 Central Hawke's Bay District Council

Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz